(Consultancy and advisory services start from 1998 onwards only)
Project Title: Advisory services on industrial effluent compliance
Client: M-SMM Sdn Bhd (subsidiary to Sumitomo Corporation, Japan). Responsibility: Consultant. Period: Dec 2006 (3 months)
Project Title: EIA for Idemitsu plant in Pasir Gudang
Client: Idemetsu. Responsibility: Head of consultancy project. Period: Oct 2005 – March 2006
Project Title: Carbon credit scheme for palm oil mills
Client: International Carbon Credit Sdn Bhd and Felda. Responsibility: Wastewater engineering expert
Period: July 2006 – now
Project Title: Detailed EIA project for reclamation of land for Ranca-Ranca port, Labuan
Client: Maritime Department, Malaysia Ministry of Transport
Responsibility: Principal consultant. Period: July 2006 – now
Project Title: Arbitration on wastewater treatment plant design and construction
Client: Genting Sanyen Sdn Bhd. Responsibility: Expert witness. Period: Oct 2005 – February 2007
Note: To provide professional judgement on detail design of the wastewater treatment plants
Project Title: Design of hybrid membrane bioreactor for palm oil mill effluent treatment
Client: Sakti Suria Sdn Bhd. Responsibility: Designer of MBR system. Period: July 2005 – Dec 2006
Note: To provide detail design of the MBR system
Project Title: Design of biogas anaerobic system for palm oil mill for Golden Hope Plantation
Client: Sakti Suria Sdn Bhd. Responsibility: Designer of anaerobic biogas production pilot plant. Period: Oct– Dec 2005
Note: To provide detail design of the biogas system
Project Title: Design of Hi-Kleen design system using WASDA
Client: PJ Bumi Berhad. Responsibility: Designer of the system. Period: July – Sept 2005
Note: To provide system to design the treatment plants
Project Title: Master plan for water development in Negeri Sembilan
Client: State of Negeri Sembilan. Responsibility: Chairman of the technical report preparation
Period: Sept – Dec 2005
Note: To propose alternatives to overcome water crisis in Seremban
Project Title: Due diligence on the 8+1 Technologies in InventQjaya Sdn. Bhd.
Client: SIRIM Berhad. Responsibility: Techical expert of membrane technology. Period: May – July 2005
Note: To provide comments on the level of technology
Project Title: Study on the Pollution Prevention and River Cleaning Project for Sungai Segget & Tebrau, Johor Bahru.
Client: Malaysia Department of Environment. Responsibility: Director of Project
Value: RM2.03 million. Status: October 2001-October 2002
Note: Principal Consultant and head of project management team, as well as developing master plan for sewerage catchment and wastewater treatment plants. Emphasis on sustainable sanitation and decentralised wastewater treatment approach.
Project Title: Study on Odor Control and Management
Client: Hualon Corporation (M) Bhd. Responsibility: Head of Project
Value: RM50,000. Status: November 2003-May 2004
Note: Principal consultant and head of project management and determination of origin of odor problems, and providing engineering design for odor control in wastewater treatment plant.
Project Title: Study on Cleaner Production Master Plan Implementation in Malaysia
Client: Malaysia Department of Environment. Responsibility: Director of Project
Value: RM320,000. Status: October 2002-October 2003
Note: Principal consultant and head of project management, and developing master plan for industralised wastewater treatment plants for reuse and recycling of treatment waste materials. The emphasis was on industrial ecology and zero emission approaches.
Project Title: Cost-effective of upgading of waste stabilization ponds.
Client: Indah Water Konsortium. Responsibility: Head of Project
Value: RM62,500. Status: Completed, April 2000
Note: Principal consultant and head of project management, and developing a new design for upgrading WSP using baffles and wetlands. The emphasis was on ecological sustainable sanitation approach.
Project Title: EIA Study for Mixed Development Project in Lot 53091/2, Kluang, Johor
Client: Tenaga Professional (Johor) Sdn. Bhd. Responsibility: Head of Project
Value: RM48,000. Status: August 2003-April 2004
Project Title: Feasibility study on reclamation project at Tanjung Kling, Malacca.
Client: Kolej Islam Melaka. Responsibility: Head of Project
Value: RM50,000. Status: Completed, 1998
Project Title: Air monitoring (every three month for three years)
Client: Steadtler (M) Sdn. Bhd., Johor Bahru. Responsibility: Head of Project
Value: RM38,400. Status: Ongoing, since 1999
Project Title: Upgading of solid-liquid separation in water treatment plant.
Client: Sibu Water Board, Sarawak. Responsibility: Head of Project
Value: RM13,000 . Status: Completed, December 1999
Project Title: Cost-effective of upgading of waste stabilization ponds.
Client: Indah Water Konsortium. Responsibility: Head of Project
Value: RM62,500. Status: Completed, April 2000
Project Title: EIA and hydraulic studies for Dangga Bay Project, Johor Bahru.
Client: Ekovest Project Management Sdn. Bhd., Johor Bahru. Responsibility: Head of EIA Project
Value: RM195,000. Status: Completed. February 2001.
Project Title: EIA for the Development of Research Center for Freshwater Fisheries, Jelebu, N. Sembilan
Client: JKR Head Quarters. Responsibility: Head of Project
Value: RM140,000. Status: Completed, March 2001.
Project Title: Action Plan on Water Management System in UTM Skudai Campus, Johor
Client: UTM. Responsibility: Head of Project
Value: RM30,000. Status: Completed, January, 2001.
Project Title: Solid and Hazardous Waste Management & Advanced Water Treatment
Client: Genesis Technology, Sarawak. Responsibility: Head of Project
Value: RM21,500. Status: Completed, November 2000
Project Title: Industrial Wastewater Treatment
Client: Genesis Technology, Sarawak. Responsibility: Head of Project
Value: RM11,500. Status: Completed, 1999