Consultancies

Yearno.RoleProgram TitleLocationTotal Income Generated (RM)
2020
 1Project LeaderTo Perform Land Survey for New Ash PondMalakoff Power Plant, Tanjung Bin, Johor.36806
 2Project LeaderSettlement Survey At Coal Workshop Building & Conveyer Area At Tanjung Bin Power Plant (TBPP)Malakoff Power Plant, Tanjung Bin, Johor.131,811
3Project LeaderTo conduct soil settlement studyMalakoff Power Plant, Tanjung Bin, Johor.209,500
 4Project LeaderEIA for Proposed Iron Ore Mine Operation at PTD 12113, Batu 10 1/2, Mukim Chaah Baru Daerah Batu Pahat, Johor.10,000
 5Project LeaderSite investigation work    Batu Pahat, Johor950
 2018
1Project MemberMelaksanakan Program Pemantauan Cerun Dan Pemasangan Peralatan Pemantauan GegeranLoji Rawatan Air Gunung Pulau, Kulai, Johor.467,000
 2Project LeaderLandfill Hotspot Detection Using Thermal Imaging Based On Drone PlatformJelutong, Pulau Pinang.9,400
 2017
 1Project MemberGeotropik and Groundwater SymposiumUniversiti Teknologi Malaysia.71,321
 2Project MemberPembaikan cerun runtuhJalan kebangsaan 3, Taman Universiti, Skudai, Johor.9,900
 3Project MemberKerja-Kerja Ujikaji Makmal Tanah serta Kerja-Kerja Berkaitan DengannyaLrt 3 Johan Setia, Klang, Selangor.16,345
 4Project MemberPelantikan Perunding Bagi Projek Lebuhraya Pan Borneo Sabah Jalan Pintas Wp 22 Lahad Datu Ke Kg. Sandau, Lahad DatuLahad Datu, Sabah.50,000
 5Project LeaderLaboratory Testing FeeUniversiti Teknologi Malaysia.4,982
 2016
 1Project MemberKerja-kerja pemasangan sistem amaran awal meramal kejadian banjir/banjir lumpur di Hutan Lipur Gunung Pulai 1, Kulai serta kerja-kerja berkaitan dengannya  Jabatan Perhutanan Negeri Johor.190,000.00
 2Project MemberLantikan terus bagi menjalankan kerja-kerja tambahan pemasangan sistem amaran awal meramal kejadian banjir/banjir lumpur di Hutan Lipur Gunung Pulai 1, Kulai serta kerja-kerja berkaitan dengannyaJabatan Perhutanan Negeri Johor.21,762.86
 2015
 1Project MemberKajian semula geologi, geoteknik dan hidrologi di persekitaran tadahan sungai air hitam besar, gunung pulai, KulaijayaJabatan Perhutanan Negeri Johor. 29,000.00
 2Project LeaderSoil investigation works for proposed site at sedili kechilAneka Alunan Sdn Bhd22,003.80
 2014
 1Project MemberPenyediaan Kurikulum Islamic universiti of MadinaUniversiti Teknologi Malaysia.333,587.75

Total Fees Received (Project Leader) = RM 425452.80

Total Fees Received (Project Member) = RM 1188916.61

Total Fees Received (Project Leader & Project Member) = RM 1614369.41