Royal Belum XPDC 4 – Day 4/6

Day 1

Day 2

Day 3

Day 4 was the day we were supposed to do a trial run of our pipes and turbine. However there were several issues that need to be settled. First was the connection between PVC pipes and HDPE pipes which was our weakest link in the system. The connection really needs to be water tight and anchored to the ground. Second the weir was still not completed at this time. Third the turbine house still needed some final touch-up where we need to do some concriting and drain building. Fourth is the connection between the HDPE pipes and the turbine. So, we were split into several groups to settle all these issues.

Sands need to be transfeered from waterfall site which is about 100m from the turbine house

Final connection from HDPE pipes to turbine house

Finishing of the turbine house.

     

Our orang asli friends having a rest.

We also realised that some of the wires in the generator and controller unit had been bitten by a mouse. Luckily they were still can be repaired and used.

 

Connection between PVC and HDPE pipes.

     

Finishing of weir construction

 

Air valve were installed at several locations

Finally at the end of the day we decided to open the dam at the weir to run our turbine.

Water coming out from an air valve

The turbine in operation

 

We got around 2V of electricity which was considerably less than what was targeted.

Air was still in the pipes.

By this time we realised that the water flow rate need to be increased. Several reasons were suggested for the slow flow rate. We were thinking that there was still a lot of air in the pipes. So we need to let the water flows until no air is left – by checking the air valve. Also it was suggested to let the pipe be full first before opening the check valve so that we get a full body of water flowing through the pipes. And finally we need to modify the weir so that the percentage of water going into the weir can be increased.

However not long after the turbine was in operation disaster strucked. The connection between the HDPE pipes and the turbine which consist of a couple of PVC bends broke. So we were forced to postpone the project to the next day until this setback can be settled.

Day 5

The views and opinions expressed in these web page(s) are strictly those of the author. The contents of these page(s) have not been reviewed or approved by the Universiti Teknologi Malaysia